Performed works:
— Commissioning started in November 2021.
— Year 2022 sees the commissioning of electrical and thermal equipment, external communication systems, intra-service communication and HVAC with the first stage to be completed in Q1 2023.
— May 2022 saw the commissioning of the external communication system between Udarnaya HPP and Kuban RDO of the main and reserve channel.
— The HPP is planned to be up and running in 2024.