Performed works:
— Functioning as the head commissioning contractor.
— Analysis of design and detailed design documentation, development of commissioning project.
— Full scope of commissioning of the power unit equipment.
— Coordination of all participants of commissioning.
— Development of detailed and technical programmes of commissioning works, equipment operation instructions.
— Commissioning and testing of heat and electrical equipment, all local ACS (LACS), engineering systems (heating, ventilation, air conditioning, etc.), fuel supply equipment, SSZShO equipment.
— Incoming control of all instrumentation and control equipment.
— Completion of the full scope of as is and operational documentation.
— Comprehensive testing, warranty tests, start-up and hot water boilers, steam boiler, turbine unit and the power unit as a whole.
— Commissioning of the facility, testing of NPRCh, AVRChM, OPRCh.
— Mode adjustment of power units with auxiliary equipment.
Equipment:
— Three steam turbines with a power of 65 MW type UTZ K-65-13.0 65 MW. manufactured by Ural Pipe Works CJSC.
— Three turbine generators TF-65-2UHL4, manufactured by ELSIB CJSC.
— Three steam boilers, manufactured by E-240-13.8-560KT, Podolsk Machine-Building Works OJSC.