Performed works:
— Technical support and control over completion of C&A.
— Comprehensive control of commissioning.
— Development of detailed grid schedule for C&A and commissioning of GTU and STU.
— Analysis of commissioning programmes, issuing comments on the programmes.
— Development of high-priority commissioning programmes.
— Determination of the critical path for completion of C&A and commissioning.
— Organisation and execution of hot commissioning of GTU.
Equipment:
— Gas turbine unit type GTE-160 manufactured by Power Machines LMZ JSC.
— Heat recovery boiler PR-226/49-7.0/0.65-510/208 (P-134) IK ZIOMAR OJSC.
— Steam turbine unit T-50/70-6.8/0.12 manufactured by Kaluga Turbine Works OJSC (KTZ).
Integrated Energy Solutions LLC © 2026 All rights reserved.