Performed works:
— Installation of bored piles, incl: Drilling 480 boreholes with a diameter of 800 mm, depth down to 15 m, installation of casing pipes, manufacture and installation of reinforcement frames, concreting.
— Reinforcement and concreting of foundations for 24 wind turbines, concrete volume 12 216 m³.
— Construction of 24 assembly and storage platforms.
— 17.5 km of on-site motor roads.
— 12 km of cable trenches for 35 kV power cables.
Equipment:
— Wind power units of V126-4.2 MW model are completed with generators with rated voltage 0.75 kV, U = 0.75/0.65 kV converters, 35/0.72 kV power transformers, WPU auxiliary equipment and 35 kV complete gas-insulated switchgear (GISG): 24 pieces.
— WPP control module with backup power supply for the module: diesel generator unit (DGU).