Performed works:
— Installation of 16 cells of new KRUM-35 kV.
— Installation of busbar bridge and connection of new 35 kV switchgear to existing transformers T-3, T-4.
— Integration of new equipment into existing systems APCS, CAEMS, FSS, RACS.
— Installation of loudspeaking and intercom in new equipment.
— Adjustment of ECA algorithms with impact on newly installed 35 kV cells.
— Comprehensive electrical installation and commissioning works.
Equipment:
— APCS manufactured by NPP Ekra LLC.
— Communication systems manufactured by NPP Ekra LLC.
— KRU-SESch-70-35 U3 manufactured by Electroshield-TM Samara GK CJSC.